ENGINEERING & PROJECT MANAGEMENT(EPM)

 


ENGINEERING AND PROJECT MANAGEMENT 
 
ENGINEERING SCOPE OF SERVICES
Phase 1: Inception, Investigation & Feasibility

Site Assessment: Conduct physical site inspections, review existing baseline data, and identify physical, environmental, or regulatory constraints. 

Surveys & Testing: Coordinate or execute necessary geotechnical investigations, topographic surveys, utility mapping, and environmental impact assessments. 

Feasibility & Concept Options: Evaluate technical alternatives, perform lifecycle cost and risk analyses, and recommend an optimal engineering solution.

Deliverables: Inception Report, Site Investigation & Survey Reports, Concept Design Options, Preliminary Cost Estimate (Class 4/5).


Phase 2: Preliminary Engineering Design (30% Design)

Basis of Design (BoD): Establish design criteria, codes, standards, load parameters, and system performance requirements.

Schematic Layouts: Develop preliminary general arrangement drawings, process flow diagrams (PFDs), single-line diagrams, and spatial coordination plans.

Authority Consultation: Initiate preliminary discussions with statutory authorities, utility providers, and permitting agencies.

Deliverables: Basis of Design Report, 30% Preliminary Drawings, Updated Cost Estimate (Class 3), Preliminary Project Schedule. 


Phase 3: Detailed Engineering Design (90%–100% IFC)

Engineering Calculations: Perform detailed structural, civil, mechanical, electrical, or process calculations using industry-approved software.

Detailed Drawings & BIM: Produce coordinated Issued-for-Construction (IFC) drawings across all relevant disciplines (and 3D BIM models, if applicable).

Technical Specifications & BOQ: Prepare detailed material/equipment specifications, Bills of Quantities (BOQ), and an Engineer’s Cost Estimate.

Permitting Support: Prepare technical documentation required to secure statutory building, environmental, and utility approvals.

Deliverables: 100% IFC Drawings (CAD/BIM & PDF), Signed Calculation Packages, Technical Specifications, Unpriced & Priced BOQ, Final Engineer's Cost Estimate (Class 1/2).


Phase 4: Procurement & Tendering Support

Tender Documentation: Compile the technical sections of the Request for Tender (RFT) for construction contractors and equipment suppliers.

Bidder Queries: Attend pre-bid meetings, conduct site walk-throughs, and issue formal technical addenda/clarifications.

Bid Evaluation: Evaluate technical submissions for compliance, participate in commercial bid comparisons, and issue a Contractor Award Recommendation.

Deliverables: Technical Tender Package, Bidder Clarification Log, Technical Bid Evaluation Report.
 
 


PROJECT MANAGEMENT SCOPE OF SERVICES
 
Phase 4: Procurement & Tendering Support

Tender Documentation: Compile the technical sections of the Request for Tender (RFT) for construction contractors and equipment suppliers.

Bidder Queries: Attend pre-bid meetings, conduct site walk-throughs, and issue formal technical addenda/clarifications.

Bid Evaluation: Evaluate technical submissions for compliance, participate in commercial bid comparisons, and issue a Contractor Award Recommendation.

Deliverables: Technical Tender Package, Bidder Clarification Log, Technical Bid Evaluation Report. 

Phase 5: Construction Supervision & Contract Administration

Design Review & Submittals: Review and approve contractor shop drawings, material submittals, method statements, and Requests for Information (RFIs).

Quality Assurance & Site Inspections: Conduct periodic (or full-time resident) site inspections to verify workmanship and adherence to IFC drawings and specifications.

Progress & Cost Control: Chair regular site progress meetings, verify contractor payment certificates, and evaluate variation orders/change requests.

Testing & Commissioning: Witness factory acceptance tests (FAT), site acceptance tests (SAT), and system commissioning.

Deliverables: Monthly Progress Reports, Inspection & Non-Conformance Reports (NCRs), Approved Shop Drawing Logs, Commissioning Certificates.

Phase 6: Project Closeout & Handover

As-Built Documentation: Review and verify the contractor's Red-Line and final As-Built drawings, Operation & Maintenance (O&M) manuals, and warranties.

Snagging & Handover: Conduct final substantial completion inspections, compile punch lists (snag lists), and issue the Taking-Over Certificate.

Defects Liability Period (DLP): Provide technical advisory during the [12-month] DLP and conduct the final defects inspection.

Deliverables: Final Project Completion Report, Verified As-Built Package, O&M Manuals, Final Defects Liability Certificate.
 

 

INTERNATIONAL STANDARD FOR COST ESTIMATES

Class 5: Concept Screening (0% to 2% design completion). Used for initial feasibility tests. Typical accuracy range is -50% to +100%.
Class 4: Study or Feasibility (1% to 15% design completion). Used to secure preliminary financing. Accuracy ranges from -30% to +50%.
Class 3: Budget Authorization (10% to 40% design completion). Anchors the official project budget. Accuracy ranges from -20% to +30%.
Class 2: Control or Tender (30% to 70% design completion). Used for checking bids from contractors. Accuracy ranges from -15% to +20%.
Class 1: Check Estimate (65% to 100% design completion). Detailed bid-grade document. Accuracy ranges from -10% to +15%.

SHE (Safety, Health, and Environment) Management
 
The Three Pillars of SHE

Safety. Preventing immediate physical accidents, injuries, and fatalities on site, such as falls from heights, trench collapses, electrocution, and heavy machinery collisions. 

Health. Protecting workers from long-term illnesses, occupational diseases, and physical strain caused by noise, hazardous dust (like silica), toxic chemicals, poor ergonomics, and extreme heat. 

Environment. Controlling how construction activities impact the surrounding area, including managing construction waste, controlling dust and noise pollution, preventing chemical spills, and protecting local waterways. 

Core Elements of Site SHE Management

 Hazard Identification and Risk Assessment (HIRA).

 Permits to Work (PTW). 

 Training and Communication. 

 Site Welfare and Infrastructure. 

 Emergency Preparedness. 

 Audits and Incident Investigation. 
 
Powered by MakeWebEasy.com
This website uses cookies for best user experience, to find out more you can go to our Privacy Policy  and  Cookies Policy